(1) Annual Risk Mitigation Implementation Plan implementation status reports must be submitted by June 1st of each year until the implementation is completed and approved by DEQ, or on a schedule approved by DEQ in the Risk Mitigation Implementation Plan and include the description of:
(2) A facility shall allow access for inspections during the implementation of the Risk Mitigation Implementation Plan upon DEQ's request or at reasonable hours.
(3) DEQ inspections and frequency may include:
(4) A final post-implementation report, or series of final reports, must be submitted 180 calendar days after the implementation completion. The report or reports shall include:
(5) Recordkeeping. The owner or operator must retain the final post-implementation report and all records related to the Risk Mitigation Implementation Plan implementation activities for ten years from the date the information is submitted to DEQ.
Statutory/Other Authority: ORS 468.020 & SB 1567 (2022)