Current through Register Vol. 63, No. 12, December 1, 2024
(1)
The annual third party verification requirements set forth in this division
apply beginning in 2022 for reports with data for calendar year 2021, and in
each year thereafter. Quarterly review conducted as part of annual verification
services that meet the requirements of this division may begin in 2022 for
reports with data for the year 2022.
(2) Each responsible entity must:
(a) Engage the services of a verification
body to perform verification under this division;
(b) Do the following before verification
services begin:
(A) Conduct a conflict of
interest evaluation in coordination with the verification body according to OAR
340-272-0500 and develop a
conflict of interest mitigation plan, if needed, according to OAR
340-272-0500. Ensure both a
complete and accurate conflict of interest evaluation and conflict of interest
mitigation plan, as applicable, are submitted to DEQ, and receive from DEQ
approval in writing to proceed with verification services; and
(B) Submit to DEQ the report that is to be
verified and attest that the data and information submitted to DEQ in the
report is true, accurate, and complete;
(c) Ensure that a verification statement is
submitted to DEQ from the verification body for each report identified under
OAR 340-272-0110 and OAR
340-272-0120 by the deadline
specified under section (3); and
(d) Ensure the requirements of this division
are met, including but not limited to, ensuring that verification services are
provided in compliance with the requirements of OAR
340-272-0300 and that a
potential for a conflict of interest is evaluated, monitored, and mitigated
according to OAR 340-272-0500;
(3) Verification deadlines.
(a) Each responsible entity must ensure that
a positive, qualified positive, or adverse verification statement is received
by DEQ from a verification body by August 31 of the year a report is submitted,
for the following reports, as applicable:
(A)
Any CFP report, as applicable under OAR
340-272-0110; and
(B) Any GHG Reporting Program emissions data
report described under OAR
340-215-0044(1)
(a) through (d), and (g), as applicable under
OAR 340-272-0120.
(b) Each responsible entity must ensure that
a positive, qualified positive, or adverse verification statement is received
by DEQ from a verification body by September 30 of the year a report is
submitted, for each GHG Reporting Program emissions data report described under
OAR 340-215-0044(1)(e) and
(f), as applicable under OAR
340-272-0120.
(c) DEQ may extend verification deadlines in
subsections (a) or (b) as necessary and will issue notice of any
extensions.
(4) Requirements for full or less intensive
verification for certain responsible entities.
(a) Responsible entities required to engage
the services of a verification body to perform annual verification of CFP
quarterly reports under OAR
340-272-0110(3),
GHG Reporting Program emissions data reports under OAR
340-272-0120(1),
or both must engage the services of a verification body to provide full
verification, as described by this division, in the first year that
verification is required under section (1), in 2023, and then in at least every
third year thereafter, if subsection (b) is applicable. Full verification is
required in any year where subsection (b) does not apply.
(b) Responsible entities required to engage
the services of a verification body to perform annual verification of CFP
quarterly reports under OAR
340-272-0110(3),
GHG Reporting Program emissions data reports under OAR
340-272-0120(1),
or both may engage the services of a verification body to provide less
intensive verification in place of full verification, for up to two years out
of every three year period, if:
(A) There has
not been a change in the verification body;
(B) A positive verification statement was
issued for the previous year; and
(C) No change of operational control of the
responsible entity occurred in the previous year.
(c) A verification body may choose to provide
full verification, at its discretion, in instances where the responsible entity
has made changes in sources, significant changes in emissions, significant
changes in data management systems, or any combination therein, occurred
compared to the previous year, based on the professional judgment of the
verification body.
(A) The verification body
must provide reasons why it opted for full verification to the responsible
entity and to DEQ.
(B) The
verification body must provide justification in the verification report if it
did not opt for full verification in instances where the total reported
emissions differ by greater than 25 percent relative to the previous year's
emissions.
(5)
Verification body and verifier rotation requirements.
(a) A responsible entity must not use the
same verification body or verifier(s) to perform verification for a period of
more than six consecutive years.
(b) A responsible entity must wait at least
three years before re-engaging the previous verification body or verifier(s) to
perform verification.
Statutory/Other Authority: ORS
468.020,
468A.050,
468A.266,
468A.271,
468A.277 &
468A.280
Statutes/Other Implemented: ORS
468A.010,
468A.015,
468A.050,
468A.265 through
468A.277 &
468A.280