This rule applies to renovation and demolition at major sources subject to the Oregon Title V Operating Permit program as defined in OAR 340-200-0020.

(1) To determine applicability of DEQ's asbestos regulations, the owner or operator of a renovation or demolition activity must thoroughly survey, using an accredited inspector, the affected area for the presence of asbestos, including nonfriable asbestos. A copy of that survey report must remain on site during a demolition or renovation activity.

(2) For demolition or renovation where no asbestos-containing material is present, the facility owner or operator, the owner or operator of a demolition or renovation activity, or the contractor must submit written notification to DEQ on an approved form. The submitter must provide notification as follows:

(a) Submit the notification, as specified in section (3) of this rule, to DEQ at least 10 days before beginning a demolition project.

(b) A notification of demolition is void if the submitter does not notify DEQ before making a change in the scheduled starting or completion date or any other substantive change.

(3) The submitter must provide the following information for each notification of demolition or renovation:

(a) Name, address, and telephone number of the person conducting the demolition or renovation;

(b) Contractor's Oregon demolition license number, if applicable;

(c) Certification that no asbestos was found during the predemolition survey and that if asbestos-containing material is uncovered during demolition the procedures found in OAR 340-248-0250 through 340-248-0280 will be followed;

(d) Description of building, structure, facility, installation, vehicle, or vessel to be demolished, including:
(A) The age and present and prior use of the facility; and

(B) Address or location of the scheduled demolition project;

(e) Major source owner or operator name, address and phone number;

(f) Scheduled starting and completion dates of demolition work; and

(g) Other information requested on DEQ form.

Statutory/Other Authority: ORS 468 & 468A

Statutes/Other Implemented: ORS 468A.745

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.